Pune to Ahilyanagar: the road and rail plans, and where they stand

Most people in Ahilyanagar measure the city by its distance from Pune. Three projects would change that journey: an elevated road out of Pune as far as Shirur, a new expressway from Pune to Chhatrapati Sambhajinagar, and a railway from Pune through Ahilyanagar and Shirdi to Nashik. None is finished. This is where each one stood when last reported.

Checked 12 November 2026 · Status: Planned, at different stages

Pune to Shirur elevated road
About 53 km, Rs 7,515 crore, bids opened September 2025
Pune to Chhatrapati Sambhajinagar expressway
Rs 25,000 crore, land acquisition slow
Pune to Ahilyanagar rail
125 km double line, survey approved
Pune to Nashik rail
Now routed through Ahilyanagar and Shirdi

Pune to Shirur elevated corridor

The state cabinet approved a six-lane elevated corridor on the Pune to Shirur stretch on 6 September 2024: 53 km, at Rs 7,515 crore (Free Press Journal). The Maharashtra State Infrastructure Development Corporation (MSIDC) took the project over from MSRDC. By 30 September 2025 technical bids had been opened, with Adani, Welspun and GR Infraprojects bidding, and a build time of four years (Punekar News).

We have not found a report of the contract being awarded.

Pune to Chhatrapati Sambhajinagar expressway

This is a new expressway estimated at Rs 25,000 crore, with a separate Rs 9,000 crore plan to renovate the existing road through Ahilyanagar. MSIDC and NHAI signed an agreement in June 2024. In March 2025 land acquisition was described as sluggish and was expected to begin in January 2026 (Free Press Journal, 25 March 2025).

The villages named in that report are in the Chhatrapati Sambhajinagar and Paithan area. We found no list of villages in Ahilyanagar district and no report on progress after January 2026.

Rail: Pune, Ahilyanagar, Shirdi, Nashik

In December 2024 the Railway Minister told the Lok Sabha that a survey had been approved for a new double line from Pune to Ahilyanagar, 125 km (Punekar News, 18 December 2024).

On 17 June 2026 he said the Pune to Nashik rail link will run through Ahilyanagar and Shirdi. The detailed project report is ready, large parts are sanctioned and work has started on some sections. The earlier direct route was dropped because of the radio telescope near Narayangaon (Free Press Journal).

We could not find the sanctioned cost or a completion date for the Pune to Ahilyanagar section.

What it means if you are looking at land nearby

These are plans at different stages, and plans slip. Do not pay more for a plot today because of a road or railway that has no contractor yet. If the plot is on a proposed route, check for acquisition first.

  • Ask the seller for the latest 7/12 extract and read the "other rights" column. Land that is being acquired usually carries an entry there.
  • Ask the talathi or the land acquisition office whether the survey number is in any acquisition notice. For a national highway these are called 3A (plan to acquire) and 3D (land now belongs to the government) notifications.
  • Check the zone of the plot on the development plan or regional plan. Land beside a highway is not always in a residential zone.
  • Read our guide on NA and gunthewari plots before you pay a token.

Homes and plots we list nearby

Questions people ask

Is there a new expressway from Pune to Ahilyanagar?

A Pune to Chhatrapati Sambhajinagar expressway estimated at Rs 25,000 crore is planned, with a separate plan to renovate the existing road through Ahilyanagar. In March 2025 land acquisition had not begun. A six-lane elevated corridor from Pune to Shirur was approved in September 2024.

Will there be a direct train from Pune to Ahilyanagar?

A survey for a new 125 km double line was approved in December 2024. In June 2026 the Railway Minister said the Pune to Nashik link will go through Ahilyanagar and Shirdi, with work started on some sections. No completion date has been given in what we read.

Sources

Every fact on this page was read on these pages. We last checked them on 12 November 2026.

  1. Free Press Journal: cabinet approves Pune-Shirur elevated corridor
  2. Punekar News, 30 September 2025: bids opened for the Pune-Shirur corridor
  3. Free Press Journal, 25 March 2025: Chhatrapati Sambhajinagar-Pune expressway land acquisition
  4. Punekar News, 18 December 2024: survey for a Pune-Ahilyanagar double line
  5. Free Press Journal, 17 June 2026: Pune-Nashik rail link via Ahilyanagar and Shirdi