Ahilyanagar · railways
Ahilyanagar-Beed-Parli Vaijnath railway: what is open and what is left
This is a new broad gauge line of 261.25 km from Ahilyanagar through Beed to Parli Vaijnath. The Railways and the Maharashtra government share the cost equally. The line has opened in stages from the Ahilyanagar end.
Checked 12 November 2026 · Status: Open up to Beed
- Full length
- 261.25 km
- Cost shared
- Railways 50%, Maharashtra 50%
- Ahilyanagar to Amalner (B)
- 99.03 km, open
- Amalner (B) to Beed
- 67.78 km, opened 17 September 2025
- Beed to Parli Vaijnath
- Being finished in 2026, opening not confirmed
What is open
The first 99.03 km, from Ahilyanagar to Amalner (B), was already carrying trains. The next 67.78 km, from Amalner (B) to Beed, was inaugurated on 17 September 2025. The stations on that section are Beed, Rajuri (Navgan), Raimoha, Vighanwadi, Jatnandur and Amalner (B) (Punekar News; Free Press Journal).
A daily Beed to Pune train (11434/11433) was announced, with its first run set for 17 September 2026. Its stops include Amalner Bhandyache, New Ashti, Narayandoho, Ahilyanagar, Shrigonda Road, Daund Chord Line and Uruli (Free Press Journal). We have not seen a report confirming the regular timetable, so check with the railway enquiry before you plan around it.
What is left: Beed to Parli Vaijnath
In April 2026 the Beed Collector inspected the corridor and said the right of way was clear, and the railway was asked to finish key works by 15 May (The Week, 12 April 2026). Later that month the track was expected to reach Parli by 31 May, with trial runs in June, and the Beed MP asked for a Parli to Pune train by 15 August 2026 (Free Press Journal, 24 April 2026).
We could not confirm whether trains have reached Parli. We will update this page when the Railways announce it.
What it means for buyers in Ahilyanagar
For people from Beed and Ashti who work or study in Ahilyanagar or Pune, the line makes the journey possible by train. We do not predict what that does to prices.
If you are buying near a station or the track, check the same things as for any plot: the zone, the NA status and whether any part of the survey number has been acquired for the railway. The 7/12 extract shows acquisition entries.
Homes and plots we list nearby
Questions people ask
Is the Ahilyanagar to Beed railway line open?
Yes. Ahilyanagar to Amalner (B), 99.03 km, opened first, and Amalner (B) to Beed, 67.78 km, was inaugurated on 17 September 2025.
Is there a direct train from Beed to Pune through Ahilyanagar?
A daily Beed to Pune train (11434/11433) stopping at Ahilyanagar was announced, with its first run set for 17 September 2026. Check the current timetable with the railway enquiry.
When will the line reach Parli Vaijnath?
In April 2026 the track was expected to reach Parli by the end of May 2026 with trial runs in June. We could not confirm that trains are running to Parli.
Sources
Every fact on this page was read on these pages. We last checked them on 12 November 2026.
- Punekar News: Amalner (B) to Beed line inaugurated
- Free Press Journal: Amalner (B)-Beed broad gauge line inaugurated
- Free Press Journal: Beed-Pune daily train set to begin
- The Week (PTI), 12 April 2026: Collector inspects the Beed-Parli Vaijnath corridor
- Free Press Journal, 24 April 2026: MP seeks Parli-Pune train by 15 August